Dept. of Trans. PROGRESS Serial No. Contract No. 15-205-09-05 03-3E1104 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 45% Location: Federal Project: 03-NEV-80-28.0 NHIM-804(200) Progress payment No. 005 Payment period ending: 07-20-15 F.D. THOMAS, INC. 217 BATEMAN DR. CENTRAL POINT OR 97502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 751,723.28 75,540.48 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 751,723.28 75,540.48 5. Mobilization 145,100.00 7,255.00 6. Total Work Completed 896,823.28 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 891,823.28 82,795.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,795.48