Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-207-15-20 03-3E2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-BUT-162-14.7/ .0 Federal Project: NONE Progress payment No. 10 Payment period ending: 06-29-10 F B D VANGUARD CONSTRUCTION INC 651 ENTERPRISE COURT LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 480,970.36 15,766.00 2.a. Extra Work 3,454.11 1,774.11 b. Adjustment Comp. -50,092.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 434,332.47 17,540.11 5. Mobilization 28,875.00 0.00 6. Total Work Completed 463,207.47 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 443,207.47 7,540.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,540.11