Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-302-11-29 03-3E3504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-50.7/50.8 Federal Project: ER-43E3(4) Progress payment No. 03 Payment period ending: 08-13-08 ODYSSEY LANDSCAPING COMPANY INC 800 W EIGHT MILE ROAD STOCKTON CA 95209 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 97,135.00 1,500.00 2.a. Extra Work b. Adjustment Comp. 4,020.00 4,020.00 3. Materials on Hand 4. Earned Subject to Retention 101,155.00 5,520.00 5. Mobilization 6. Total Work Completed 101,155.00 7. Deductions -8,747.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 92,408.00 25,520.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,520.00