Dept. of Trans. PROGRESS Serial No. Contract No. 08-264-15-33 03-3E4204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 32% 03-SIE-5725 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-19-08 OWENS CONST 44 LEONARD LANE COLFAX CA 95713 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 66,213.50 66,213.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 66,213.50 66,213.50 5. Mobilization 6. Total Work Completed 66,213.50 7. Deductions 8. a.Contract Retentions -3,310.68 -3,310.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 62,902.82 62,902.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,902.82