Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-066-08-38 03-3E4404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-GLE-5734 Federal Project: NONE Progress payment No. 07 Payment period ending: 02-16-12 UNITED BUILDING CONTRACTORS INC P O BOX 6039 CHICO CA 95927 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 467,588.00 29,398.86 2.a. Extra Work 17,374.71 7,667.21 b. Adjustment Comp. -2,372.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 482,590.01 37,066.07 5. Mobilization 6. Total Work Completed 482,590.01 7. Deductions -40,000.00 -30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 442,590.01 7,066.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,066.07