Dept. of Trans. PROGRESS Serial No. Contract No. 10-168-12-46 03-3E4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 39% 03-ED-50-27.9/28.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-10 KOCH EXCAVATING INC P O BOX 909 PENN VALLEY CA 95946 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 288,034.91 179,668.94 2.a. Extra Work 800.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 288,834.91 179,668.94 5. Mobilization 6. Total Work Completed 288,834.91 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 288,834.91 179,668.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179,668.94