Dept. of Trans. PROGRESS Serial No. Contract No. 10-203-11-09 03-3E4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 59% 03-ED-50-27.9/28.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-20-10 KOCH EXCAVATING INC P O BOX 909 PENN VALLEY CA 95946 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 331,713.58 43,678.67 2.a. Extra Work 5,750.00 4,950.00 b. Adjustment Comp. -475.40 -475.40 3. Materials on Hand 4. Earned Subject to Retention 336,988.18 48,153.27 5. Mobilization 6. Total Work Completed 336,988.18 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 336,988.18 48,153.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,153.27