Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-007-13-59 03-3E5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-99-20.8/ .0 Federal Project: ACHS-PO99(517) NHG-P099(517) Progress payment No. 05 Payment period ending: 11-20-09 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 472,286.00 3,400.00 2.a. Extra Work 14,500.00 0.00 b. Adjustment Comp. -7,575.00 -7,575.00 3. Materials on Hand 4. Earned Subject to Retention 479,211.00 -4,175.00 5. Mobilization 6. Total Work Completed 479,211.00 7. Deductions -20,000.00 -12,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 459,211.00 -16,175.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -16,175.00