Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-132-10-30 03-3E5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-99-0.8/22.6 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-04-11 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA SUITE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 278,444.20 0.00 2.a. Extra Work 132,160.12 13,680.06 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 410,604.32 13,680.06 5. Mobilization 26,000.00 0.00 6. Total Work Completed 436,604.32 7. Deductions -1,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 435,604.32 23,680.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,680.06