Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-14-18 03-3E6304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 0% 03-ED-49-9.6/10.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-18-12 DOUG VEERKAMP GENERAL ENGINEERING INC 2585 COLD SPRINGS ROAD PLACERVILLE CA 95667 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,937.64 22,377.64 2.a. Extra Work 29,885.93 29,885.93 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 53,823.57 52,263.57 5. Mobilization 35,775.00 35,775.00 6. Total Work Completed 89,598.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 89,598.57 88,038.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 88,038.57