Dept. of Trans. PROGRESS Serial No. Contract No. 10-323-09-59 03-3E8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 68% 03-SAC-99-21.9/24.2 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-19-10 PROFESSIONAL CONSTRUCTION SERVICES 3309 VINCENT ROAD PLEASANT HILL CA 94523 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 139,327.57 27,925.06 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 139,327.57 27,925.06 5. Mobilization 26,250.00 0.00 6. Total Work Completed 165,577.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 165,577.57 27,925.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,925.06