Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 11-305-08-28 03-3E8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 03-SAC-99-21.9/24.2 Federal Project: NONE Progress payment No. 07 Payment period ending: 10-20-11 CONSTRUCTION FUNDS CONTROL SERVICES 1330 ARNOLD DRIVE, SUITE 242 MARTINEZ, CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 766,300.48 174,290.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 766,300.48 174,290.80 5. Mobilization 35,000.00 0.00 6. Total Work Completed 801,300.48 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 801,300.48 174,290.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 174,290.80