Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-207-15-53 03-3E9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SUT-99-40.2/ .0 Federal Project: NONE Progress payment No. 07 Payment period ending: 06-22-10 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 348,863.75 9,080.00 2.a. Extra Work 51,971.39 49,371.39 b. Adjustment Comp. 8,388.49 1,590.89 3. Materials on Hand 4. Earned Subject to Retention 409,223.63 60,042.28 5. Mobilization 6. Total Work Completed 409,223.63 7. Deductions -14,000.00 -14,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 395,223.63 46,042.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,042.28