Dept. of Trans. PROGRESS Serial No. Contract No. 24-325-14-53 03-3F0604 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 63% Location: Federal Project: 03-GLE-162-76.3/78.6 ACST-P162(41) Progress payment No. 035 Payment period ending: 11-20-24 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,932,674.55 911,363.60 2. a. Extra Work 6,929,398.15 821,256.59 b. Adustment Comp. 3,986,697.60 0.00 3. Materials on Hand 699,008.00 -624,377.74 4. Earned Subject to Retention 64,547,778.30 1,108,242.45 5. Mobilization 6,686,030.00 0.00 6. Total Work Completed 70,534,800.30 7. Deductions -10,000.00 9,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 71,223,808.30 1,117,242.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,117,242.45