Dept. of Trans. PROGRESS Serial No. Contract No. 24-296-14-35 03-3F0704 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 29% Location: Federal Project: 03-SAC-51-0.2/3.5 ACNH-P051(39) Progress payment No. 014 Payment period ending: 10-20-24 AMERICAN RIVER CONSTRUCTORS A JOINT VENTURE PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,448,894.37 4,060,439.88 2. a. Extra Work 91,797.02 80,746.27 b. Adustment Comp. 3,519.60 0.00 3. Materials on Hand 117,067.50 0.00 4. Earned Subject to Retention 53,661,278.49 4,141,186.15 5. Mobilization 19,657,422.00 6,486,949.26 6. Total Work Completed 73,201,632.99 7. Deductions -10,000.25 -0.09 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 73,308,700.24 10,628,135.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,628,135.32