Dept. of Trans. PROGRESS Serial No. Contract No. 25-080-09-46 03-3F0704 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 40% Location: Federal Project: 03-SAC-51-0.2/3.5 ACNH-P051(39) Progress payment No. 019 Payment period ending: 03-20-25 AMERICAN RIVER CONSTRUCTORS A JOINT VENTURE PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 68,686,029.92 2,948,411.23 2. a. Extra Work 142,303.19 1,762.99 b. Adustment Comp. 351,229.65 0.00 3. Materials on Hand 676,414.72 179,253.92 4. Earned Subject to Retention 69,855,977.48 3,129,428.14 5. Mobilization 19,657,422.00 0.00 6. Total Work Completed 88,836,984.76 7. Deductions -35,500.25 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 89,477,899.23 3,119,428.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,119,428.14