Dept. of Trans. PROGRESS Serial No. Contract No. 25-143-08-30 03-3F0704 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 44% Location: Federal Project: 03-SAC-51-0.2/3.5 ACNH-P051(39) Progress payment No. 021 Payment period ending: 05-20-25 AMERICAN RIVER CONSTRUCTORS A JOINT VENTURE PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 73,209,923.85 2,560,864.65 2. a. Extra Work 197,935.13 17,494.40 b. Adustment Comp. 351,229.65 0.00 3. Materials on Hand 883,600.16 0.00 4. Earned Subject to Retention 74,642,688.79 2,578,359.05 5. Mobilization 19,657,422.00 0.00 6. Total Work Completed 93,416,510.63 7. Deductions -25,500.25 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 94,274,610.54 2,568,359.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,568,359.05