Dept. of Trans. PROGRESS Serial No. Contract No. 15-322-11-22 03-3F0804 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 59% Location: Federal Project: 03-SAC-51-0.2/1.1 BHNH-P051(28) Progress payment No. 002 Payment period ending: 11-20-15 MYERS AND SONS CONSTRUCTION, LP 4600 NORTHGATE BLVD, SUITE 10 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 463,792.63 108,296.50 2. a. Extra Work 2,454.59 2,454.59 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 466,247.22 110,751.09 5. Mobilization 370,650.00 123,550.00 6. Total Work Completed 836,897.22 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 831,897.22 229,301.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 229,301.09