Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-239-11-31 03-3F0804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-SAC-51-0.2/1.1 BHNH-P051(28) Progress payment No. 007 Payment period ending: 05-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,491,851.36 66,800.75 2. a. Extra Work 33,758.94 31,304.35 b. Adustment Comp. -24,254.64 -24,254.64 3. Materials on Hand 4. Earned Subject to Retention 4,501,355.66 73,850.46 5. Mobilization 494,200.00 0.00 6. Total Work Completed 4,995,555.66 7. Deductions -20,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,975,555.66 78,850.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 78,850.46