Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-013-07-48 03-3F0804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-SAC-51-0.2/1.1 BHNH-P051(28) Progress payment No. 008 Payment period ending: 05-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,491,851.36 0.00 2. a. Extra Work 94,052.37 60,293.43 b. Adustment Comp. -24,254.64 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,561,649.09 60,293.43 5. Mobilization 494,200.00 0.00 6. Total Work Completed 5,055,849.09 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,035,849.09 60,293.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 60,293.43