Dept. of Trans. PROGRESS Serial No. Contract No. 20-328-15-07 03-3F0904 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 55% Location: Federal Project: 03-SAC-160-20.9/R45.0 B1NH-000C(494) Progress payment No. 011 Payment period ending: 11-20-20 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,711,180.70 1,002,159.20 2. a. Extra Work 418,619.91 50,125.21 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 18,129,800.61 1,052,284.41 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 20,329,800.61 7. Deductions -13,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,316,800.61 1,042,284.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,042,284.41