Dept. of Trans. PROGRESS Serial No. Contract No. 21-145-10-18 03-3F0904 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 55% Location: Federal Project: 03-SAC-160-20.9/R45.0 B1NH-000C(494) Progress payment No. 017 Payment period ending: 05-20-21 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,584,338.57 995,623.62 2. a. Extra Work 1,053,947.28 80,717.18 b. Adustment Comp. 31,488.56 0.00 3. Materials on Hand 125,556.43 125,556.43 4. Earned Subject to Retention 22,795,330.84 1,201,897.23 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 24,869,774.41 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,985,330.84 1,211,897.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,211,897.23