Dept. of Trans. PROGRESS Serial No. Contract No. 16-145-13-33 03-3F1704 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 30% Location: Federal Project: 03-SAC-5-20.0/25.0 NH-000C(392) Progress payment No. 002 Payment period ending: 05-20-16 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD #260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 781,132.90 462,680.95 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 781,132.90 462,680.95 5. Mobilization 80,747.15 16,999.40 6. Total Work Completed 861,880.05 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 856,880.05 474,680.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 474,680.35