Dept. of Trans. PROGRESS Serial No. Contract No. 25-170-10-34 03-3F23U4 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 97% Location: Federal Project: 03-PLA-80-0.1/2.2 ACIM-803(252) 03-PLA-80-4.1/6.0 Progress payment No. 024 Payment period ending: 06-20-25 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,091,123.20 1,196,747.03 2. a. Extra Work 2,488,642.52 194,362.29 b. Adustment Comp. 315,846.62 79,245.00 3. Materials on Hand 4. Earned Subject to Retention 34,895,612.34 1,470,354.32 5. Mobilization 2,930,000.00 0.00 6. Total Work Completed 37,825,612.34 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,825,612.34 1,471,354.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,471,354.32