Dept. of Trans. PROGRESS Serial No. Contract No. 13-326-13-34 03-3F2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 83% 03-PLA-80-4.1/R19.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-19-13 MC GUIRE PACIFIC CONSTRUCTOR'S P O BOX 4072 AUBURN CA 95604 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 803,393.41 511,160.25 2.a. Extra Work 10,431.00 10,431.00 b. Adjustment Comp. -8,475.60 -8,475.60 3. Materials on Hand 4. Earned Subject to Retention 805,348.81 513,115.65 5. Mobilization 6. Total Work Completed 805,348.81 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 805,348.81 513,115.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 513,115.65