Dept. of Trans. PROGRESS Serial No. Contract No. 15-323-12-32 03-3F3404 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 21% Location: Federal Project: 03-SAC-160-L7.0 BHNH-P160(24) Progress payment No. 003 Payment period ending: 11-20-15 FD THOMAS, INC 217 BATEMAN DR CENTRAL POINT OR 97502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 892,803.93 616,309.57 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 892,803.93 616,309.57 5. Mobilization 673,800.00 673,800.00 6. Total Work Completed 1,566,603.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,566,603.93 1,290,109.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,290,109.57