Dept. of Trans. PROGRESS Serial No. Contract No. 14-169-12-04 03-3F4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 31% 03-PLA-49-0.9/ .0 Federal Project: SSTP-000C(365) Progress payment No. 03 Payment period ending: 06-16-14 DREAMBUILDER CONSTRUCTION CORP DBA DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 243,288.30 228,138.30 2.a. Extra Work 27,774.07 27,774.07 b. Adjustment Comp. 121,885.08 121,885.08 3. Materials on Hand 4. Earned Subject to Retention 392,947.45 377,797.45 5. Mobilization 76,055.39 76,055.39 6. Total Work Completed 469,002.84 7. Deductions -15,000.00 -15,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 454,002.84 438,852.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 438,852.84