Dept. of Trans. PROGRESS Serial No. Contract No. 20-328-15-27 03-3F5104 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 43% Location: Federal Project: 03-YUB-20-R18.1/M20.1 HSNH-P020(189) Progress payment No. 013 Payment period ending: 11-20-20 FLATIRON WEST, INC. 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,679,534.96 1,157,410.48 2. a. Extra Work 587,515.00 25,564.89 b. Adustment Comp. 227,219.77 0.00 3. Materials on Hand 0.00 -20,471.82 4. Earned Subject to Retention 22,494,269.73 1,162,503.55 5. Mobilization 3,350,000.00 0.00 6. Total Work Completed 25,844,269.73 7. Deductions -36,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,808,269.73 1,152,503.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,152,503.55