Dept. of Trans. PROGRESS Serial No. Contract No. 21-084-14-34 03-3F5104 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 59% Location: Federal Project: 03-YUB-20-R18.1/M20.1 HSNH-P020(189) Progress payment No. 017 Payment period ending: 03-20-21 FLATIRON WEST, INC. 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,932,062.78 804,317.24 2. a. Extra Work 695,662.71 46,631.18 b. Adustment Comp. 227,219.77 0.00 3. Materials on Hand 566,197.00 566,197.00 4. Earned Subject to Retention 27,421,142.26 1,417,145.42 5. Mobilization 3,350,000.00 0.00 6. Total Work Completed 30,204,945.26 7. Deductions -10,000.00 18,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,761,142.26 1,435,145.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,435,145.42