Dept. of Trans. PROGRESS Serial No. Contract No. 20-358-09-50 03-3F5404 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 51% Location: Federal Project: 03-SAC-99-4.5/5.5 ACNH-X067(81) 03-SAC-160-44.5/44.5 Progress payment No. 009 Payment period ending: 12-20-20 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,840,072.51 5,154.40 2. a. Extra Work 811,192.80 25,930.10 b. Adustment Comp. 3. Materials on Hand 1,204,091.57 -0.01 4. Earned Subject to Retention 11,855,356.88 31,084.49 5. Mobilization 1,700,000.00 0.00 6. Total Work Completed 12,351,265.31 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,545,356.88 21,084.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,084.49