Dept. of Trans. PROGRESS Serial No. Contract No. 18-109-10-28 03-3F5704 PROGRESS PAYMENT VOUCHER %complete: %time: 6% 9% Location: Federal Project: 03-SAC-12-0.0/0.4 ACNH-P012(123) 03-SOL-12-26.3/26.4 Progress payment No. 003 Payment period ending: 04-20-18 CERTIFIED COATINGS CO. 2320 CORDELIA RD FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 620,009.57 282,784.03 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 620,009.57 282,784.03 5. Mobilization 368,050.00 220,830.00 6. Total Work Completed 988,059.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 988,059.57 503,614.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 503,614.03