Dept. of Trans. FINAL Serial No. Contract No. 16-028-11-31 03-3F6504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-NEV-89-0.0/8.7 STP-P089(115) Progress payment No. 007 Payment period ending: 11-17-15 GRANITE CONSTRUCTION COMPANY PO BOX 720 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,275,671.33 0.00 2. a. Extra Work 157,377.16 0.00 b. Adustment Comp. -158,192.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,274,855.95 0.00 5. Mobilization 379,334.00 0.00 6. Total Work Completed 3,654,189.95 7. Deductions 0.00 12,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,654,189.95 12,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,000.00