Dept. of Trans. PROGRESS Serial No. Contract No. 15-146-11-51 03-3F6704 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 1% Location: Federal Project: 03-ED-49-23.9/35.0 STP-P049(159) Progress payment No. 001 Payment period ending: 05-20-15 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BOULEVARD STE 260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,168.51 72,168.51 2. a. Extra Work b. Adustment Comp. 1,510.48 1,510.48 3. Materials on Hand 4. Earned Subject to Retention 73,678.99 73,678.99 5. Mobilization 6. Total Work Completed 73,678.99 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 63,678.99 63,678.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,678.99