Dept. of Trans. PROGRESS Serial No. Contract No. 15-237-10-25 03-3F6704 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 75% Location: Federal Project: 03-ED-49-23.9/35.0 STP-P049(159) Progress payment No. 004 Payment period ending: 08-20-15 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BOULEVARD STE 260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,517,758.12 675,377.36 2. a. Extra Work 63,115.46 10,109.25 b. Adustment Comp. -2,479.04 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,578,394.54 685,486.61 5. Mobilization 128,250.00 0.00 6. Total Work Completed 2,706,644.54 7. Deductions -329,616.89 -175,871.65 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,377,027.65 509,614.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 509,614.96