Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-075-08-12 03-3F6704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-ED-49-23.9/35.0 STP-P049(159) Progress payment No. 011 Payment period ending: 03-04-16 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD #260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,218,958.09 0.00 2. a. Extra Work 160,316.06 19,446.41 b. Adustment Comp. -204,373.94 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,174,900.21 19,446.41 5. Mobilization 135,000.00 0.00 6. Total Work Completed 5,309,900.21 7. Deductions -113,400.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,196,500.21 19,446.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,446.41