Dept. of Trans. PROGRESS Serial No. Contract No. 17-355-14-32 03-3F7604 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 70% Location: Federal Project: 03-BUT-191-6.8/8.6 ACHS-STP1-9(100) Progress payment No. 009 Payment period ending: 12-20-17 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,445,290.64 33,285.00 2. a. Extra Work 807,765.79 330,284.74 b. Adustment Comp. 8,492.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,261,548.43 363,569.74 5. Mobilization 3,025,000.00 0.00 6. Total Work Completed 16,286,548.43 7. Deductions -1,374,633.89 25,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,911,914.54 388,569.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 388,569.74