Dept. of Trans. PROGRESS Serial No. Contract No. 14-324-13-37 03-3F7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 55% 03-SUT-99-13.6/26.1 Federal Project: HSST-000C(374) Progress payment No. 03 Payment period ending: 11-18-14 CHRISP COMPANY 43650 OSGOOD ROAD FREMONT CA 94539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 979,155.01 648,174.64 2.a. Extra Work b. Adjustment Comp. -17,340.00 -17,340.00 3. Materials on Hand 4. Earned Subject to Retention 961,815.01 630,834.64 5. Mobilization 101,525.00 5,076.25 6. Total Work Completed 1,063,340.01 7. Deductions -8,000.00 -8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,055,340.01 627,910.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 627,910.89