Dept. of Trans. PROGRESS Serial No. Contract No. 14-357-13-02 03-3F7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 60% 03-SUT-99-13.6/26.1 Federal Project: HSST-000C(374) Progress payment No. 04 Payment period ending: 12-18-14 CHRISP COMPANY 43650 OSGOOD ROAD FREMONT CA 94539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,148,717.89 169,562.88 2.a. Extra Work b. Adjustment Comp. -3,609.18 13,730.82 3. Materials on Hand 4. Earned Subject to Retention 1,145,108.71 183,293.70 5. Mobilization 101,525.00 0.00 6. Total Work Completed 1,246,633.71 7. Deductions -16,000.00 -8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,230,633.71 175,293.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 175,293.70