Dept. of Trans. PROGRESS Serial No. Contract No. 16-293-11-49 03-3F8304 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 12% Location: Federal Project: 03-SAC-5-1.0/1.0 STP-000C(428) Progress payment No. 001 Payment period ending: 10-20-16 M&M ELECTRIC DBA MAY-HAN ELECTRIC 1600 AUBURN BLVD SACRAMENTO CA 95815 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 533,083.28 533,083.28 2. a. Extra Work b. Adustment Comp. -2,100.00 -2,100.00 3. Materials on Hand 133,889.00 133,889.00 4. Earned Subject to Retention 664,872.28 664,872.28 5. Mobilization 9,002.20 9,002.20 6. Total Work Completed 539,985.48 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 673,874.48 673,874.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 673,874.48