Dept. of Trans. PROGRESS Serial No. Contract No. 17-207-15-13 03-3F8304 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 82% Location: Federal Project: 03-SAC-5-1.0/1.0 STP-000C(428) Progress payment No. 007 Payment period ending: 07-20-17 M&M ELECTRIC DBA MAY-HAN ELECTRIC 1600 AUBURN BLVD SACRAMENTO CA 95815 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,061,815.26 255,994.10 2. a. Extra Work b. Adustment Comp. -2,100.00 0.00 3. Materials on Hand 188,790.00 -112,692.44 4. Earned Subject to Retention 2,248,505.26 143,301.66 5. Mobilization 9,476.00 0.00 6. Total Work Completed 2,069,191.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,257,981.26 143,301.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,301.66