Dept. of Trans. PROGRESS Serial No. Contract No. 21-208-11-16 03-3F99U4 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 52% Location: Federal Project: 03-SUT-99-39.2/41.4 ACNH-P099(649) Progress payment No. 013 Payment period ending: 07-20-21 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,787,921.65 1,579,248.51 2. a. Extra Work 2,663,394.30 241,842.37 b. Adustment Comp. 632,956.50 16,734.25 3. Materials on Hand 512,854.32 -2,734.12 4. Earned Subject to Retention 19,597,126.77 1,835,091.01 5. Mobilization 2,790,000.00 0.00 6. Total Work Completed 21,874,272.45 7. Deductions -33,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,354,126.77 1,835,091.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,835,091.01