Dept. of Trans. PROGRESS Serial No. Contract No. 24-306-07-47 03-3G0104 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 96% Location: Federal Project: 03-SIE-49-15.6/17.0 NONE Progress payment No. 003 Payment period ending: 10-15-24 ALL AMERICAN CONSTRUCTION INC 1700 ACACIA AVENUE SUTTER CA 95982 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 911,312.55 51,089.45 2. a. Extra Work 28,169.94 28,169.94 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 939,482.49 79,259.39 5. Mobilization 6. Total Work Completed 939,482.49 7. Deductions -30,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 909,482.49 49,259.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,259.39