Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-268-10-56 03-3G1304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-VAR NONE Progress payment No. 003 Payment period ending: 09-16-25 DEES BURKE ENGINEERING CONSTRUCTORS LLC 207 W STATE ST ONTARIO CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,650,273.30 426,843.93 2. a. Extra Work 28,746.46 28,746.46 b. Adustment Comp. -3,372.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,675,647.76 455,590.39 5. Mobilization 180,000.00 0.00 6. Total Work Completed 1,855,647.76 7. Deductions -45,559.04 -43,259.04 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,810,088.72 412,331.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 412,331.35