Dept. of Trans. PROGRESS Serial No. Contract No. 25-237-10-39 03-3G4004 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 25% Location: Federal Project: 03-YOL-16-10.0/15.0 NONE Progress payment No. 001 Payment period ending: 08-20-25 ALL AMERICAN CONSTRUCTION INC 1700 ACACIA AVENUE SUTTER CA 95982 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 888,039.51 888,039.51 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 888,039.51 888,039.51 5. Mobilization 6. Total Work Completed 888,039.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 888,039.51 888,039.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 888,039.51