Dept. of Trans. PROGRESS Serial No. Contract No. 26-295-09-40 03-3G5104 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 26% Location: Federal Project: 03-ED-49-25.2/26.2 NONE Progress payment No. 002 Payment period ending: 10-20-26 DOUG VEERKAMP GENERAL ENGINEERING INC. 3701 TRADE WAY CAMERON PARK CA 95682 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 200,271.44 149,988.44 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 200,271.44 149,988.44 5. Mobilization 19,903.17 4,190.14 6. Total Work Completed 220,174.61 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 215,174.61 149,178.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,178.58