Dept. of Trans. PROGRESS Serial No. Contract No. 25-325-07-30 03-3G6204 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 60% Location: Federal Project: 03-YOL-5-R22.8/R28.9 NONE Progress payment No. 003 Payment period ending: 11-20-25 ALL AMERICAN CONSTRUCTION INC 1700 ACACIA AVENUE SUTTER CA 95982 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,215,170.28 -89,613.68 2. a. Extra Work b. Adustment Comp. 310,624.79 310,624.79 3. Materials on Hand 4. Earned Subject to Retention 2,525,795.07 221,011.11 5. Mobilization 6. Total Work Completed 2,525,795.07 7. Deductions -9,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,516,795.07 217,011.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 217,011.11