Dept. of Trans. PROGRESS Serial No. Contract No. 25-353-08-51 03-3G7404 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 75% Location: Federal Project: 03-NEV-80-156.0/15.6 NONE Progress payment No. 003 Payment period ending: 12-20-25 ACCO ENGINEERED SYSTEMS, INC. 888 EAST WALNUT STREET PASADENA, CA 91101 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 535,349.55 277,754.16 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 535,349.55 277,754.16 5. Mobilization 6. Total Work Completed 535,349.55 7. Deductions -12,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 523,349.55 275,754.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,754.16