Dept. of Trans. PROGRESS Serial No. Contract No. 26-029-08-35 03-3G7404 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 75% Location: Federal Project: 03-NEV-80-156.0/15.6 NONE Progress payment No. 004 Payment period ending: 01-20-26 ACCO ENGINEERED SYSTEMS, INC. 888 EAST WALNUT STREET PASADENA, CA 91101 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 622,236.53 86,886.98 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 622,236.53 86,886.98 5. Mobilization 6. Total Work Completed 622,236.53 7. Deductions -12,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 610,236.53 86,886.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 86,886.98