Dept. of Trans. PROGRESS Serial No. Contract No. 26-055-06-44 03-3G7404 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 75% Location: Federal Project: 03-NEV-80-156.0/15.6 NONE Progress payment No. 005 Payment period ending: 02-20-26 ACCO ENGINEERED SYSTEMS, INC. 888 EAST WALNUT STREET PASADENA, CA 91101 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 698,777.56 76,541.03 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 698,777.56 76,541.03 5. Mobilization 6. Total Work Completed 698,777.56 7. Deductions -12,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 686,777.56 76,541.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 76,541.03