Dept. of Trans. PROGRESS Serial No. Contract No. 17-117-13-39 03-3H0504 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 20% Location: Federal Project: 03-NEV-80-12.5/21.2 NONE Progress payment No. 001 Payment period ending: 04-20-17 ACME CONCRETE PAVING INC 4124 E BROADWAY AVE SPOKANE WA 99202 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 478,983.78 478,983.78 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 478,983.78 478,983.78 5. Mobilization 6. Total Work Completed 478,983.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 478,983.78 478,983.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 478,983.78